Become an Expert in Project Management
https://projectmanagementexperts.org/lates-pmi-scheduling-professional-pmi-sp-exam-questions/
Export date: Fri Apr 20 20:02:32 2018 / +0000 GMT

Lates PMI Scheduling Professional PMI-SP Exam Questions


New Updated PMI-SP Exam Questions PMI-SP PDF dumps! Welcome to download the newest PMI-SP VCE dumps: https://www.dumpsschool.com/PMI-SP-exam-dumps.html 1(326 Questions)


Keywords: PMI-SP exam dumps, PMI-SP exam questions, PMI-SP exam questions, PMI-SP VCE dumps, PMI-SP PDF dumps, PMI-SP practice tests, PMI-SP study guide, PMI-SP braindumps, PMI-SP


PMI Scheduling Professional certification exam as a profession has an extraordinary evolution over the last few years. PMI-SP PMI-SP exam is the forerunner in validating credentials against. Here are updated PMI-SP exam questions, which will help you to test the quality features of DumpsSchool exam preparation material completely free. You can purchase the full product once you are satisfied with the product.


Question: 1


Once the project's WBS has been created what process may happen next?

A. Estimate activity resources
B. Define activities
C. Estimate activity durations
D. Sequence activities

Answer: B

Explanation:
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created. Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid. Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.

Question: 2

Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

A. Precedence Diagramming Method
B. Schedule network template
C. Dependency determination
D. Activity on the Node

Answer: A

Explanation:
The Precedence Diagramming Method uses both predecessors and successors as nodes in the project network diagram. The PDM approach is the most common network diagram approach used. Answer option C is incorrect. Dependency determination identifies the order of the project work. Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram. Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.

Question: 3

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A. Push technique
B. Many-to-many
C. One-to-one
D. Pull technique

Answer: A

Explanation:
Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email. Answer option C is incorrect. One-to-one technique describes a conversation between two people. Answer option B is incorrect. Many-to-many technique describes a conversation between many people. Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.

Question: 4

Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?

A. Perform resource leveling for the project.
B. Crash the project schedule.
C. Fast track the project.
D. Remove things from the project scope.

Answer: C

Explanation:
Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in

sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks. Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified. Answer option A is incorrect. Resource leveling can actually increase the project duration. Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.

Question: 5

The Define Activities process is the first process in the project time management knowledge are

a. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment. Which one of the following is not an output of the Define Activities process?

A. Activity list
B. Milestone list
C. Activity attributes
D. Project document updates

Answer: D

Explanation:
Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following: Activity list Activity attributes Resource calendars Answer option A is incorrect. The activity list is an output of the define activities process. Answer option C is incorrect. The activity attributes is an output of the define activities process. Answer option B is incorrect. The milestone list is an output of the define activities process.

Question: 6

Examine the figure given below:

If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

A. Three days
B. One day
C. Four days
D. Zero days

Answer: B

Explanation:
Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late. Answer option D is incorrect. There is one day of float still available for Activity H. Answer options A and C are incorrect. These are not the valid answers, as there is just one day of float available for Activity H.

Question: 7

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

A. A significant point in the project
B. A goal of reaching a significant delivery of project benefits by an identified date
C. An imposed date for the project to reach a given point

D. The completion of a project activity that is crucial to project completion

Answer: A

Question: 8

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

A. Process boundaries
B. Process configuration
C. Targets for improved performance
D. Identification of project risks

Answer: D

Explanation:
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.
Links:
  1. https://www.dumpsschool.com/PMI-SP-exam-dumps.html
Post date: 2017-10-10 04:00:00
Post date GMT: 2017-10-10 04:00:00

Post modified date: 2017-10-10 06:12:40
Post modified date GMT: 2017-10-10 06:12:40

Export date: Fri Apr 20 20:02:32 2018 / +0000 GMT
This page was exported from Become an Expert in Project Management [ https://projectmanagementexperts.org ]
Export of Post and Page has been powered by [ Universal Post Manager ] plugin from www.ProfProjects.com